'Shovel ready': National Grid helps 20GW of clean energy projects jump connections queue

Stuart Stone
clock • 3 min read
T-pylon diamond insulators being installed on Hinkley Connection Project Credit: National Grid
Image:

T-pylon diamond insulators being installed on Hinkley Connection Project Credit: National Grid

National Grid moves capacity equivalent to six Hinkley Point C nuclear power stations up connections queue, promising major boost to energy storage developers

National Grid has today announced it is bringing forward the grid connection date for up to 20GW of "shovel ready" clean energy projects in England and Wales by up to five years. The grid operator said...

To continue reading this article...

Join BusinessGreen

In just a few clicks you can start your free BusinessGreen Lite membership for 12 months, providing you access to:

  • Three complimentary articles per month covering the latest real-time news, analysis, and opinion from Europe’s leading source of information on the Green economy and business
  • Receive important and breaking news stories via our daily news alert
  • Our weekly newsletter with the best of the week’s green business news and analysis

Join now

 

Already a BusinessGreen member?

Login

More on Energy

Electrify now, but decarbonise later?

Electrify now, but decarbonise later?

Electrification must not be used as a pretext to prolong our dependence on these fuels, writes explorer campaigner and Solar Impulse Foundation president Bertrand Piccard

Bertrand Piccard
clock 17 November 2026 • 3 min read
Study: UK business electricity bills could rise by more than 25 per cent every year to 2030

Study: UK business electricity bills could rise by more than 25 per cent every year to 2030

Cornwall Insight expects UK firms of all shapes and sizes to face higher electricity bills for the rest of the decade, as calls grow for accelerated shift to clean, homegrown electricity system

Stuart Stone
clock 16 November 2026 • 5 min read
Gas begins flowing from Jackdaw as government faces calls to block Rosebank

Gas begins flowing from Jackdaw as government faces calls to block Rosebank

Controversial North Sea projects begins fossil gas production as government faces growing pressure - including from Labour MPs - to block huge Rosebank oil project near Shetland

Michael Holder
clock 16 November 2026 • 5 min read