'Shovel ready': National Grid helps 20GW of clean energy projects jump connections queue

Stuart Stone
clock • 3 min read
T-pylon diamond insulators being installed on Hinkley Connection Project Credit: National Grid
Image:

T-pylon diamond insulators being installed on Hinkley Connection Project Credit: National Grid

National Grid moves capacity equivalent to six Hinkley Point C nuclear power stations up connections queue, promising major boost to energy storage developers

National Grid has today announced it is bringing forward the grid connection date for up to 20GW of "shovel ready" clean energy projects in England and Wales by up to five years. The grid operator said...

To continue reading this article...

Join BusinessGreen

In just a few clicks you can start your free BusinessGreen Lite membership for 12 months, providing you access to:

  • Three complimentary articles per month covering the latest real-time news, analysis, and opinion from Europe’s leading source of information on the Green economy and business
  • Receive important and breaking news stories via our daily news alert
  • Our weekly newsletter with the best of the week’s green business news and analysis

Join now

 

Already a BusinessGreen member?

Login

More on Energy

Fossil fuel importer, or electrostate? The choice is ours

Fossil fuel importer, or electrostate? The choice is ours

If the UK seizes the moment it can build an energy system that powers a more competitive, more secure, and more prosperous Britain, writes Laura Sandys

Laura Sandys
clock 12 May 2026 • 5 min read
E.ON strikes deal to snap up OVO's UK retail business

E.ON strikes deal to snap up OVO's UK retail business

Combined firms set to become UK's largest retail energy supplier and ramp up efforts to deliver flexible grid services and domestic clean technologies

Michael Holder
clock 11 May 2026 • 5 min read
Why do we ignore obvious energy security solutions?

Why do we ignore obvious energy security solutions?

Even in the midst of a severe global fossil fuel energy crisis, energy efficiency measures - supported by electrification and digital technologies - are still too often overlooked, writes Nicola Cullen from the Climate Group

Nicola Cullen, Climate Group
clock 07 May 2026 • 4 min read