'Shovel ready': National Grid helps 20GW of clean energy projects jump connections queue

Stuart Stone
clock • 3 min read
T-pylon diamond insulators being installed on Hinkley Connection Project Credit: National Grid
Image:

T-pylon diamond insulators being installed on Hinkley Connection Project Credit: National Grid

National Grid moves capacity equivalent to six Hinkley Point C nuclear power stations up connections queue, promising major boost to energy storage developers

National Grid has today announced it is bringing forward the grid connection date for up to 20GW of "shovel ready" clean energy projects in England and Wales by up to five years. The grid operator said...

To continue reading this article...

Join BusinessGreen

In just a few clicks you can start your free BusinessGreen Lite membership for 12 months, providing you access to:

  • Three complimentary articles per month covering the latest real-time news, analysis, and opinion from Europe’s leading source of information on the Green economy and business
  • Receive important and breaking news stories via our daily news alert
  • Our weekly newsletter with the best of the week’s green business news and analysis

Join now

 

Already a BusinessGreen member?

Login

More on Energy

How reaching net zero could cut global fuel costs by $1tr a year

How reaching net zero could cut global fuel costs by $1tr a year

New modelling from BloombergNEF suggests investing just 0.7 per cent of GDP in the net zero transition could unlock huge financial savings - and avert a rolling climate crisis

James Murray
clock 04 September 2025 • 8 min read
Bolton Wanderers FC kicks off new smart grid service

Bolton Wanderers FC kicks off new smart grid service

Football club teams up with Voltaris to install flexible grid technology that reduces power demand during peak periods

clock 04 September 2025 • 2 min read
'Power Shift': Greenpeace urges government to move gas power plants out of the wholesale power market

'Power Shift': Greenpeace urges government to move gas power plants out of the wholesale power market

New report calculates that moving gas-fired power stations into a strategic reserve underpinned by a regulated asset base model could maintain energy security and save billpayers £5bn a year

Stuart Stone
clock 04 September 2025 • 7 min read