Government targets renewables grid connection bottleneck

Connect and Manage proposals designed to accelerate grid connection for remote wind farms

By BusinessGreen.com Staff

04 Mar 2010

Be the first to comment

Wind farm

The government yesterday released long-awaited proposals to reform the grid connection regime in the UK and tackle the bottlenecks that have delayed the opening of numerous wind farms.

The proposals, dubbed Connect and Manage, have been set out as part of a new consultation that will run until the end of the month. They aim to speed up the time it takes to connect new energy generation projects to the grid, on the understanding they will then closely manage their energy output to ensure they stay within grid capacities.

Energy minister David Kidney said the changes to grid connection rules would particularly benefit renewable energy projects, many of which are found in remote locations and, as a result, have faced major difficulties securing grid connections.

"Access to the electricity grid has been one of the key barriers to the generation of renewable energy in this country," said Kidney. "There is currently around 78 gigawatts of prospective new generation capacity – some 160 projects – that are waiting to be connected to the grid, including over 19 gigawatts from renewable sources."

He added that the new rules would help projects get "hooked up to the grid as soon as they are ready – helping in the shift to low carbon, secure energy supplies".

Under existing rules, new grid connections are not approved until all the necessary grid upgrade work has been done in an area to support new connections. Renewable energy developers have consistently argued that this approach favours large-scale traditional power plants and has resulted in some completed wind farms waiting up to nine years for a grid connection.

The Connect and Manage model aims to ease the bottlenecks by allowing completed projects to connect to the grid and start generating power as soon as their local connection has been built, without having to wait for wider network reinforcement to be completed.

Under the terms of the connection agreement, National Grid would then manage the increased constraints on the network; for example, potentially requesting that wind farms scale back output at certain times, before the completion of wider grid reinforcement work.

The government said the additional costs associated with the grid constraints would be "socialised equally" across all generators and suppliers in order to ensure that new generators do not face punitive charges.

WHAT DO YOU THINK? Add your comment

  

Greg Barker has said that despite cuts to solar incentives the industry will continue to grow this year - is he right?

2%

6%

8%

84%

INSIGHT

Submit your email address and we'll send a link to a personal newsletter control panel


Mechanical Integrity Engineer

09 Feb 2012

Mechanical Integrity Engineer, 35,000-45,000, Midlands A global power organization are looking to identify a Mechanical Integrity Engineer to become part of a globally accalimed engineer department. Delivering R&D Projects in relation to the business' GAS and Steam Turbine operations - the role will challenge the engineers mechanical design capabilities and integrity of company products. The succe

APC

Guidelines for specification of data centre power density

The science and practical application of an improved method for the specification of power and cooling infrastructure for data centres

Quocirca

Powering the data centre

A look at alternative approaches to managing energy for cost and/or sustainability reasons in data centres