Marine Current Turbines (MCT) has this week completed the installation of its 1.2MW SeaGen tidal energy system in Strangford Narrows in Northern Ireland.
The company has started a three-month commissioning and testing period and says it is on track to begin feeding energy to the grid later this summer.
It will also undertake a major £2m environmental impact assessment with scientists from Queens University in Belfast and St Andrews University which aims to monitor the effects of the system's twin turbines on local wildlife.
The company said that every effort had been taken to ensure the underwater turbines did not disrupt marine life, including the fitting of a sonar system to monitor the local seal population.
The SeaGen system is the world's first "commercial scale" tidal generator and will operate for up to 20 hours per day, providing enough power for up to 1,000 homes.
Martin Wright, managing director of MCT, said the installation was a " ground-breaking operation" that had attracted global media attention.
The project has led the way for a major tidal energy farm off the coast of North Wales. MCT is working with energy giant npower on the 10.5MW project, which it hopes to have operational by 2012.
SeaGen system expected to be deployed off coast of Northern Ireland by the end of the week 01 Apr 2008
Marine Current Turbines is poised to install its 1.2MW SeaGen system at Strangford Lough in Northern Ireland and connect it to the grid 12 Feb 2008
Proposals could open up most of the UK's continental shelf to wind farms as the government seeks to generate enough energy to power all the country's homes 10 Dec 2007
Focus on energy savings through fuel efficiency for homes and public and commercial buildings 04 Jul 2008
ActionAid accuses G8 of driving more people into poverty by pursing biofuels and cutting agri-aid 04 Jul 2008
Businesses' new found focus on the environment may be welcome, but according to Conrad MacKerron, it is taking attention away from workers' rights issues – and the credibility of the entire green business movement could be at risk 03 Jul 2008
It may be a year old, but as Dell's Jonathan Perry explains, firms looking to get rid of their old IT kit still need to pay attention to the WEEE directive 02 Jul 2008
Telling customers about your environmental targets is all well and good but, as Paul Thomas argues, they are meaningless if you do not know how they are to be achieved 01 Jul 2008