20 Mar 2009
The world's first commercial wave energy project is on the brink of collapse after its main backer went into administration last week, casting doubt over the future of a project that has already been dogged by technical problems.
The Aguçadoura project was a joint venture between Edinburgh-based Pelamis Wave Power, Australian energy developer Babcock & Brown, Energias de Portugal (EdP) and Portuguese electrical engineering firm Efacec.
But Australian-listed investment specialist Babcock and Brown, a majority investor in the £7m project, which as part of a consortium with EdP and Efacec holds a 77 per cent stake, was placed into voluntary administration last week, casting doubt over the future of the scheme.
The consortium successfully installed three of Pelamis' snake-like wave generators three miles off the north coast of Portugal last autumn, hailing the project as the first commercial wave energy project to provide power to the grid.
But in mid-November, all three generators were removed from the water because of leaks in the buoyancy tanks. Further technical problems have followed and cannot be repaired until a new backer is found to replace Babcock and Brown. The units are currently sitting idle in Leixões harbour.
Max Carcas, spokesman for Pelamis, told the Guardian newspaper that the technical problems were not serious and would be relatively easy to fix once an investor is found.
"In a project of this nature, the world's first wave energy plant, it's inevitable that there will be niggles and issues to tackle," he said. "We have had nothing that isn't expected."
However, he admitted the project was currently "in a state of limbo" while the company seeks to raise fresh financing.
Despite the setback, Pelamis' technology is continuing to attract interest from customers. Last month, energy firm E.ON placed an order with the company for its next generation of converters, known as the P-2.
The P2, which is 180m long, 50m longer than the devices in Portugal, will be installed at the European Marine Energy Centre in Orkney and will be fully operational by 2010.
E.ON told the Guardian that despite the problems with the Portugal project, the Orkney installation was likely to go ahead.
LATEST STORIES ABOUT ENERGY
YOU MAY ALSO LIKE
LATEST JOBS
TODAY'S TOP STORIES
HIGHLIGHT
Solar sector warns proposed cuts to feed-in tariffs would make it impossible for them to deliver promised rates of return
INSIGHT
INSIGHT
The science and practical application of an improved method for the specification of power and cooling infrastructure for data centres
A look at alternative approaches to managing energy for cost and/or sustainability reasons in data centres
WHAT DO YOU THINK? Add your comment
Patent RO 108893. Dynamic Engine for Vave Energy Catching.
Did you know that Romania has a technical solution with the highest efficiency to capture wave power?. Patent 108893 entitled Dynamic Engine for Sea Wave Energy Catching. A pioneering invention. It is estimated that “dynamic engine” has the ability to catching wave energy at a rate of over 80% while the other technical solutions known worldwide, are not able to capture wave energy with a higher percentage of about 10-15%. Cosma Vasile Romania. E-mail cosma.vasile@yahoo.com
Posted by cosma vasile, 26 Apr 2011