Report: UK industrial sites could face costly grid constraints by 2030

Michael Holder
clock • 4 min read
Port Talbot steelworks is in the process of shifting away from fossil fuels via electrification | Credit: iStock
Image:

Port Talbot steelworks is in the process of shifting away from fossil fuels via electrification | Credit: iStock

Urgent investment and policy action is needed to avoid looming power grid constraints for large UK industrial sites, Aldersgate Group warns

More than 40 per cent of large UK industrial sites are set to face costly and disruptive power constraints by the end of the decade, without urgent investment to shore up Britain's grid as electrification...

To continue reading this article...

Join BusinessGreen

In just a few clicks you can start your free BusinessGreen Lite membership for 12 months, providing you access to:

  • Three complimentary articles per month covering the latest real-time news, analysis, and opinion from Europe’s leading source of information on the Green economy and business
  • Receive important and breaking news stories via our daily news alert
  • Our weekly newsletter with the best of the week’s green business news and analysis

Join now

 

Already a BusinessGreen member?

Login

More on Infrastructure

Study: Underground cables are 4.5 times more expensive than overhead lines

Study: Underground cables are 4.5 times more expensive than overhead lines

Government Minister hails analysis as further evidence "pylons are the best option for billpayers"

James Murray
clock 29 April 2025 • 4 min read
'UK's largest': Statera Energy secures planning consent for major green hydrogen project

'UK's largest': Statera Energy secures planning consent for major green hydrogen project

Kintore Hydrogen facility expected to deliver 500MW of capacity by 2030, before expanding to 3GW in the subsequent decade

Michael Holder
clock 28 April 2025 • 2 min read
'Failed to deliver': Spending watchdog warns government off track to meet water targets

'Failed to deliver': Spending watchdog warns government off track to meet water targets

NAO warns insufficient investment and repeated delays mean sector will struggle to deliver 30 new water infrastructure projects

clock 25 April 2025 • 5 min read